NTL Project – Sweden
We have successfully completed another project in Sweden for Nordic Timber Labs.
We have successfully completed another project in Sweden for Nordic Timber Labs. Our first meeting took place almost two years ago at the Trä & Teknik 2024 fair. At that time, we had no idea what kind of client we were about to meet – two young entrepreneurs who now run a large company and placed their trust in us.
After a series of in-person meetings, site visits, and a tour of our production facility in Jihlava, we reached an agreement, and the project was completed at the end of 2025/2026.
The kiln is now running at full capacity – many thanks also to DryTech for providing the technology.
Project specifications:
- kiln type: KAD2x6PVA-Hybrid + control room
- capacity: 2 × 110 m³
- year of implementation: 2026