Here is a selection of recent projects we have delivered for customers across different countries. Each implementation has its own brief, conditions and story.

Project NTL – Sweden

Client: Nordic Timber Labs, Sweden  |  Industry: wood processing
Kiln type: KAD2x6PVA-Hybrid + control room  |  Capacity: 2 × 110 m³  |  Year of implementation: 2026

NTL Sweden
NTL Sweden
NTL Sweden

Assignment

The client was looking for a way to increase drying capacity while reducing energy consumption. The solution also needed to be reliable and ready for future growth.

Solution

Based on a series of meetings and site visits in Sweden as well as at KATRES production in Jihlava, we designed a custom timber kiln tailored to the specific operation. Scope of delivery:

  • technical design
  • kiln manufacturing
  • complete installation and commissioning
  • integration of DryTech technology

Implementation

The project was developed step by step from the first meeting at a trade fair to final installation. A strong focus was placed on smooth integration and reliable start-up.

Result

The kiln is now running at full capacity and delivers:

  • increased drying capacity
  • improved energy efficiency
  • consistent drying quality

We stay in touch and support our clients even after commissioning – from service to day-to-day operation support.

Cooperation

The project was carried out in cooperation with DryTech.

Facing a similar challenge? Let’s talk: Contacts


Project JK Wood – Finland

Client: JK Wood, Finland  |  Industry: sawmilling / timber processing
Kiln type: KAD2x6PVA-Hybrid + control room  |  Capacity: 2 × 110 m³  |  Year of implementation: 2026

JK Wood Finland
JK Wood Finland
JK Wood Finland

Assignment

The client needed to increase drying capacity and optimize performance in demanding Nordic climate conditions. Reliability during winter operation was a key requirement.

Solution

We designed and delivered custom timber kilns adapted to the specific conditions of the Finnish market. Scope of delivery:

  • tailored technical design
  • kiln manufacturing
  • on-site installation
  • commissioning

Implementation

The contract was signed in June 2025. Thanks to good coordination and experienced installation teams, the project was completed on schedule despite challenging conditions.

Result

The kilns were commissioned at the beginning of the year and deliver:

  • increased drying capacity
  • stable operation in cold climates
  • improved energy efficiency

Our work doesn’t end with delivery. We provide warranty and post-warranty service, including technical support and consultation.

Cooperation

The project was supported by our local sales representative.

Planning to expand your capacity? Get in touch: Contacts


Project CARMAN WOOD – Czech Republic

Client: CARMAN WOOD, Hradec nad Moravicí, Czech Republic  |  Industry: timber processing
Kiln type: KAD1x5S + KAD1x8K  |  Capacity: 50 m³ + 58 m³  |  Year of implementation: 2025

Carman Wood CZ
Carman Wood CZ
Carman Wood CZ

Assignment

The client required a new custom-built timber kiln tailored to their operation, enabling efficient drying capacity planning.

Solution

We designed and delivered a dual-chamber timber kiln, fully adapted to the client’s requirements. Scope of delivery:

  • technical design
  • manufacturing
  • on-site installation
  • commissioning

Implementation

The project was completed in approximately 6 months from contract signing to handover. The installation and start-up were carried out according to schedule.

Result

The solution provides:

  • a reliable drying process tailored to the operation
  • sufficient capacity for current production
  • readiness for future growth

We also provide long-term service and technical support, including post-warranty assistance.

Looking for a similar solution? Get in touch: Contacts